Gravenhurst Road Rehabilitation And Resurfacing Starting May 27

Road rehabilitation and resurfacing work will start the week of May 27 in two areas of the community.

The upcoming work consists of drainage improvements, culvert replacements, pulverization of existing asphalt, road base grading and compacting, hot mix asphalt paving, granular shouldering, and boulevard restorations.

The work will take place in the following areas:

Kilworthy Road area (starting May 27 to Aug. 30)

This work involves Kilworthy Road, from Highway 11 to just west of Arthur Schulz Road.

Additionally, the project includes a 150-metre section of Arthur Schulz Road, starting from the intersection with Kilworthy Road.

Another section of the project involves Tower Crescent, starting from the intersection with Kilworthy Road.

Narrows Road area (starting May 27 to Aug. 30)

This work involves Narrows Road, from Muskoka Road 169 to North Sunset Bay Road.